OPERATIONS AND PRESENCE

EXPANDING CAPACITIES AND CAPABILITIES

Manufacturing Facilities

Vijayanagar Works (ISP)

Hot Rolled (HR), Cold Rolled (CR), Galvanised (GI) and Galvalume (GL), colour-coated products, wire rods, TMT

12.5 MTPA crude steel

5 MTPA under commissioning, further addition of 1.5 MTPA by
FY 2024-25

Bhushan Power and Steel Ltd. Jharsuguda

HR, CR, Galvanised (GI) and Galvalume (GL), colourcoated products, TMT, slabs, billets, cable tape, black pipe, precision tubes

3.5 MTPA crude steel

1.5 MTPA under commissioning in phases

Raigarh Works

Rebars, alloy special steel products,
slabs, billets

0.95 MTPA crude steel

Dolvi Works (ISP)

HR, TMT

10 MTPA crude steel

further addition of 5 MTPA by
FY 2027-28

Salem Works (ISP)

Wire rod, alloy long products, billets/blooms

1 MTPA crude steel

Salav Works

Direct Reduced Iron (DRI) / Hot Briquetted Iron (HRI)

0.9 MTPA DRI/HBI

Mivaan Steels Limited, Raipur

Billets, Ferro alloys, Structures

0.25 MTPA crude steel

Key Products
Capacity

50 MTPA

Expected domestic capacity by FY 2030-31

Downstream Operations

Anjar Works

Steel plates and coils

1.2 MTPA

Kalmeshwar Works

GI/GL, colour-coated Products

0.96 MTPA GI/GL

Tarapur Works

GI/GL, colour-coated products, tin plate

0.73 MTPA GI/GL

0.50 MTPA tin plate

Rajpura Works

Tin plate, colour-coated products

0.12 MTPA tin plate

0.31 MTPA colour coated products

Vasind Works

GI/GL, colour-coated Products & CRCA

1.42 MTPA GI/GL

0.5 MTPA CRCA

Khopoli and Bawal Works

HRPO, GI/GL, colour-coated products

0.72 MTPA GI/GL

National Steels and Agro Industries Limited (Dhar, MP)

Colour coil, pre-painted profile sheets, galvanised corrugated sheets

0.35 MTPA GI/GL

Neotrex Steel Private Ltd. (Vijayanagar)

Low-relaxation pre-stressed concrete
steel strands

72,000 tonnes per annum LRPC

with addition of 72,000 tonnes per annum
by FY 2024-25

Mines

25.9 MnT

Captive iron ore production

0.9 BnT

Odisha iron ore reserves

0.45 BnT

Maharashtra and Goa’s iron ore reserves

0.25 BnT

Karnataka iron ore reserves

0.38 BnT

Jharkhand and Chhattisgarh coal reserves

International Manufacturing Units

JSW Steel USA
Ohio

1.5 MNTPA crude steel

3 MNTPA finishing capacity

Baytown

1.2 MNTPA Plate mill

0.55 MNTPA Pipe mill

JSW Steel Italy Piombino S.p.A
Piombino

Rails, wire rods, bars and grinding balls

1.3 MTPA finishing capacity

Project Highlights

VIJAYANAGAR

  • JSW Vijayanagar Metallics Limited, a wholly owned subsidiary of the Company, commissioned the Hot Strip Mill facility in March 2024. The commercial production and sales also commenced in March 2024. The entire 5 MTPA integrated facility of JVML is expected to be commissioned in Q2 of
    FY 2024-25 and the ramp-up of the integrated facility is expected by end of Q3 FY 2024-25.
  • Coke Oven Battery capacity of 0.75 MTPA was commissioned in FY 2023-24 resulting in reduction of procurement of coke from third parties. Further 0.75 MTPA coke oven project is expected to start commissioning from Q2 of FY 2024-25.

DOLVI

Announced capacity expansion by
5 MTPA as part of the Phase-III expansion project taking, the total capacity to 15 MTPA.

BPSL

Expansion by 1.5 MTPA to 5 MTPA is under commissioning and expected to be ramped up by the end of Q3 of FY 2024-25.

DOWNSTREAM

0.12 MTPA colour coating line in Jammu & Kashmir is expected to be commissioned by Q2 of
FY 2024-25.